ATE Evaluation Time Line |
| Evaluation project work to date and time line
|
Year 1:
- April 1 1999: Award received to begin project work.
- April - August 1999: ATE documents reviewed for background information and initial assessment conducted. Staff and advisors contracted. Initial set of indicators drafted.
- June 1999: Interim surveys piloted to test initial web-based system and to assist the ATE program staff at NSF in their monitoring of center and project progress.
- August 1999: Project staff met with Evaluator Group for input into indicators and data collection processes.
- October 1999: Project staff attended ATE PI meeting and conducted evaluation workshop with project and center staff to share information and receive feedback on current indicators and survey items.
- November 1999: Project staff met with Advisory Panel for advice on various data collection issues.
- February 2000: Survey and systems piloted with 10-15 projects and centers.
|
Year 2:
- Spring 2000: Survey field-tested.
- May 2000: Project staff met with Evaluator Group for input on the survey pilot data and advice on the site visits proposal.
- Summer 2000: Status Report 1 finalized.
- Fall 2000:
- October 2000: Project staff met with Advisory Panel for advice on site visit and Survey 2001 planning.
- October 2000: Project staff attended ATE PI meeting and conducted workshops with project/center staff to share information and receive feedback.
- Conducted site visits to projects and centers.
- Completed Status Report 2.
- Finalized Survey 2001 instrument and procedures.
- Developed and made available web page reports and
information.
- January-February 2001: Completed site visits to projects/centers.
- February 2001: Made Survey 2001 available to projects/centers for completion.
|
Year 3:
- May 2001: Summary "raw" survey data made available to participating projects/centers.
- May 2001: Focus group conducted with PIs & NSF re Survey 2002.
- July 2001: Completed the Survey 2001 report draft.
- October 2001: Project staff attended ATE PI meeting and conducted workshops with project/center staff to share information and receive feedback.
- Completed a series of issue papers based on survey and site visit data.
- Developed and made available additional web page reports and information (brochures, newsletter, issue papers, survey 2002 summary).
- Completed a site visit handbook.
|
Year 4:
- February 2002: Made Survey 2002 available to projects/centers for completion
- May 2002: Summary "raw" survey data made available to participating projects/centers
- July 2002: Completed the Survey 2002 report draft
- July 2002: Met with Advisory Panel for advice on targeted studies planning
- August 2002: Made Survey 2002 summary and PowerPoint information available on the Web page
- October 2002: Project staff to attend ATE PI meeting and conduct workshops with project/center staff to share information and receive feedback
- November 2002: Final Survey 2002 report to be made available on the Web page
- February 2003: Make Survey 2003 available to projects/centers for completion
|